Over the years, AJAY has the distinction of designing and constructing bridges of varying styles for different purposes.

The variety of construction work undertaken by the company speaks volumes about its versatility.

Fly Over & Rob

Fly Over & Rob Current Projects

Name of work:
Construction of Fly Over Bridge on Zundal along S. P. Ring Road in AUDA area.
Location :
Zundal Circle, Ahmedabad, Gujarat
Client :
The Executive Engineer, Ahmedabad Urban Development Corporation, Ahmedabad
Project Cost:
Rs. 609.94 Million
Name of work:
Development of N.H – 147 (Old NH – 8 C) including 6-lanning with service road on either side from km 31/300 to 35/480 (Package – III) in the state of Gujarat on EPC basis.
Location :
Sarkhej - Gandhinagar Highway, Ahmedabad, Gujarat
Client :
The Executive Engineer, National Highway Division, Ahmedabad
Project Cost:
Rs. 2660 Millions
Name of work:
Construciton of Road Over Bridge (four lane) Nr. Village Dastan in Lieu of LC No.17/A at Rly. Km. 18/4-5 b/w STns Chalthan & Gangadhara for Surat-Bardoli Road (Old NH.6)
Location:
Dastan, Bardoli, Gujarat
Client :
The Managing Director, Gujarat State Road Devlopment Corporation, Gandhinagar
Project Cost :
Rs. 598.64 Millions
Name of work:
Construction of 2 Nos. Two Lane ROBs (including approaches & LHS) in lieu of Level crossings No. 81 & 153 at Km. 500/4-5 between Khimel - Falna Section & Km. 629/9-630/0 at Iqbalgarh Yard of Madar-Palanpur Section of Ajmer Division of North Western Railway. Ajay-Chetan (J/V) Ajay - 51% (Value of Contract 5007.49x51%)
Location:
Falna & Iqbalgadh, Rajsthan
Client :
Dy. Chief Project Manager/EN/I, DFCCIL, Ajmer
Project Cost :
Rs. 255.38 Millions
Name of work:
Construction of Six lane ROB with LHS including Electrification work in lieu of L.C. 211 Dantli, Goner Road on JP-DLI Railway Line, Jaipur
Location:
Dantali, Jaipur, Rajsthan
Client :
The Executive Engineer,Jaipur Devlopment Authority, Jaipur
Project Cost :
Rs. 616.58 Millions
Name of work:
Construction of ROB's on DFCC Route in Lieu of (1) L.C. No. 166 - I.R. Km 651/2-3 between Karjoda - Palanpur (2) L.C No. 188 - I.R. KM 681/2-3 between Dharewada to Siddhapur (3) L.C. No. 191- I.R. Ch-685/2-3 between Siddhapur-Kamli.
Location:
Siddhpur, Gujarat
Client :
The Executive Engineer, National Highway Division, Ahmedabad
Project Cost :
Rs. 637.81 Millions

Under Pass

Under Pass Current Projects

Name of work:
Construction of Underpass on LC No. 162-B at Botad on Botad Salangpur Barwala Road.
Location:
Botad, Sarangpur, Gujarat
Client :
The Executive Engineer Bhavnagar R and B Division Bhavnagar
Project Cost :
Rs. 165.63 Millions